we’ve worked with Some great PARTNERs

Springhill Suites by Marriott

HOTEL : Complete site Prep, Excavation, concrete, & Asphalt paving

NEED: Located on the bank of Henry’s Fork, Mack’s Inn Springhill Inn Suites in Island Park required a specialized approach. High ground water, proximity to the river, unique site conditions, and a tight construction schedule dictated by weather required flexibility. Thompson was hired in part because of our ability to handle change orders with the Rexburg Springhill Suites.

SOLUTION:  To meet project timelines, Thompson worked with client engineers to manage evolving requirements. Site plans were changed over 24 times to accommodate unexpected conditions and requirements like high sub water, high snowpack / runoff, drainage (working extensively with DEQ), and bedrock excavation. Adopting a collaborative “On-site Engineering” approach, Thompson worked with project engineers to adjust grades, expand a turn lane for state highway 20 (with all the coordination), work around existing utilities, provide hot asphalt from over 2 hours away, and provide additional site concrete for another contractor to meet deadlines. Our last contribution was to finish paving in October (past the normal season in Idaho) to obtain a certificate of occupancy in time for the April opening date.

OUTCOME: Springhill Suites was able to open on schedule, meeting their obligation to pre-sold reservation holders. The general contractor provided steak dinners to our entire crew for going above and beyond to meet the opening date, and sent signed us up to finish paving their Moab, Utah Springhill Suites.

 

Madison Field House

Education : grading, Concrete, & Indoor / Outdoor paving - 45,000 SQ FT

NEED: Madison School District contracted for an indoor fieldhouse with track, turf, and tennis courts to facilitate year-round athletics during the Idaho winter season. They needed contractors with specialized concrete, asphalt paving, and site preparation skills to meet the strict tolerances and unique requirements for indoor turf.

SOLUTION: The Madison School District passed a $27M bond for the new fieldhouse. Thompson Excavation & Asphalt handled all excavation and site preparation, which started with adding material to raise the grade 2.5 ft for drainage. We handled excavation for water and sewer, footings, grading with laser guided equipment to meet strict tolerances, and collaborated with a specialized artificial turf contractor to prepare the sub layers for indoor turf fields. We provided concrete for footings, sidewalks, and curbs. Asphalt paving included tennis courts (indoor and outdoor), indoor running track (a combination of seamless concrete and asphalt), and parking lots.

OUTCOME: According to Madison School Board Trustee Holly Allen, the new facility is a major game-changer for Madison athletics, which has had difficulty competing with Boise due to a shortened outdoor season. Officials expect the fieldhouse to help level the playing field, and boost athletic programs. The project was completed on schedule while maintaining an open campus, and absorbing both change orders and the expanded scope of outdoor tennis courts.

 

BYU Idaho Spori Annex

Education : bedrock Excavation, drainage, & concrete

NEED: Much of BYU Idaho’s new construction is affected by the lava bedrock directly under much of the campus. The university needed a large scale, full service contractor capable of navigating change orders, city requirements, and working around / with existing utilities.

SOLUTION: Thompson provided extensive bedrock demo and removal to allow adequate stormwater drainage. We excavated foundation and utilities, coordinating with the City of Rexburg to tie into existing infrastructure (street, septic, water) while maintaining traffic throughput. We provided site concrete, city curb & gutter, tied into BYU Idaho’s steam ice removal system, and worked around (even underneath) existing mechanical facilities to maintain and connect to services. We adjusted site access and scheduling to accommodate continued student access to the surrounding campus.

Additionally, when scheduling conflicts jeopardized the project, we took on additional scope to install the “best concrete stairs at BYUI”. Our attention to detail on those those concrete stairs led to additional unscoped campus concrete work “since we were there”.

OUTCOME: Thompson’s flexibility with change orders and coordination with multiple outside entities helped complete the Spori Annex in 2021. Students maintained access to adjacent facilities, municipal traffic remained unimpaired, and Thompson met the added challenge of change orders and excavating bedrock without significant project delays.